One stop service, More professional.

Tel

+86-13580480068
You are here: Home / Service / SPC and LVT Click Flooring: Installation, Gaps and Storage

SPC and LVT Click Flooring: Installation, Gaps and Storage

Views: 0     Author: Site Editor     Publish Time: 2026-11-06      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
sharethis sharing button

Technical guide · Pandaboard

SPC and LVT Click Flooring: Installation, Gaps and Storage

Direct answer

SPC and LVT click flooring is typically 4–6 mm thick in 1220×180 mm planks, joined by a click profile and laid floating with no adhesive. The substrate must be flat to 2 mm over 2 m with moisture of 2.5% or less (CM method) and covered by a vapor barrier lapped at least 200 mm. Leave 8–10 mm at every wall, column and door frame, hidden by the skirting. Let packs sit flat in the room 24 hours at 18–28 °C, or the joints load unevenly and open at the seams.

Interior click flooring (SPC, LVT, laminate) is laid floating: the floor is not bonded to the substrate, the planks are joined by the click profile into one continuous sheet, and a movement gap is left at every perimeter. Success depends almost entirely on two things — substrate flatness and the expansion gap.

The two most common mistakes① Laying on an unleveled substrate (click profiles break and the floor creaks within two months); ② no perimeter gap (the whole floor bulges in summer and cannot be pressed flat).

01Key specifications and suitability

Parameter

Typical range (confirm on order)

Standard size

1220×180 / 600×300 mm

Thickness

4–6 mm (SPC), 4.5–5 mm (LVT)

Substrate flatness

≤2 mm over 2 m

Substrate moisture

≤2.5% (CM method)

Expansion gap

8–10 mm at perimeter

Service condition

18–28 °C, RH 40–70%

Suitable

  • Living rooms, bedrooms and studies

  • Offices and retail floors

  • Renovation over sound existing tile or timber

  • Rooms with underfloor heating (surface ≤27 °C)

  • Fast refits that must be walkable the same day

Not suitable

  • Wet rooms, shower areas and laundries

  • Unenclosed balconies and outdoor floors

  • New concrete still above the moisture limit

  • Factories and warehouses with forklift traffic

  • Sunrooms with more than 15 °C day-night swing

02Preparation Before Installation

2.1 Substrate Requirements

Table 2-1 Substrate control values

Item

Requirement

Test method

Flatness

≤2 mm/2 m

2 m straightedge + feeler gauge, 3 points per 10 m²

Moisture content

≤2.5 % (CM method) / ≤8 % (resistance method)

Moisture meter

Strength

No dusting, no hollow spots

Scratch test, small hammer

Cleanliness

No grease, no dust, no ridges

Visual

Environment

18 – 25 °C, 40 – 70 % RH

Thermo-hygrometer

2.2 Materials and Tools

Flooring, vapor barrier (≥0.2 mm), skirting, transition strips, tapping block, pull bar, tape measure, pencil, cutter / saw, spirit level.

Parts list and reference quantities:Per 100 m² of floor, floating installation; includes wastage. Allow 5–8 % in irregular rooms.

Material

Specification

Reference quantity per 100 m²

Flooring

e.g. 1220×180, 8–12 mm

105 m²

Underlay

2–3 mm IXPE / EVA with foil

105 m²

Skirting

matched to flooring

per room perimeter

Transition strip

at doorways and material changes

per opening

Edge sealant

neutral silicone

per perimeter

Flooring adhesive

for full or spot bonding

0.3–0.5 kg/m²

2.3 Delivery and Acclimatization

  • Deliver the flooring flat; leave the sealed packs in the installation room for 24–48 h to reach room temperature;

  • Never open the packs and stand planks against a wall (they bow);

  • One batch number per space: mixed batches give color differences and click tolerance problems.

03Floating Installation Steps

image.png

Figure 1 Floor build-up Substrate → vapor barrier → flooring; 8~10 expansion gap at all walls, hidden by the skirting.

  1. Clean and level - Remove dust and scrape off ridges; fill depressions with self-leveling compound or repair mortar, flatness ≤2 mm/2 m.

  2. Lay the vapor barrier - Cover the full area with ≥0.2 mm barrier, lap ≥100, seal seams with tape, turn up 50 at the walls.

  3. Set the laying direction - Along the main light source or the walking direction; the long edge parallel to the long wall.

  4. Mark the datum line - Leave 8–10 at the wall and mark the first row line.

  5. Lay the first row - Tongue toward the wall, hold the 8–10 gap with spacers; align the end joint and press down.

  6. Work row by row - Stagger the second row ≥300; insert the plank at 20°–30° and press down until it clicks.

  7. Last row - Measure and cut, width ≥50; pull the joint closed with a pull bar.

  8. Perimeter - Cover perimeter gaps with the skirting; fit a transition strip at doorways; cut 10 clearance around pipes and fit a collar.

  9. Cleaning and curing - No traffic and no water for 24 h; normal use after 48 h.

Three locations for expansion gaps① All walls: 8–10, continuous; ② Doorways and thresholds: break the floor and fit a transition strip; ③ Large areas: a transition joint where a run exceeds 12 m (or width >8 m). Miss one and the floor will bulge in summer.

04Special Locations

  • Underfloor heating: heat up gradually (5 °C per day), surface temperature ≤27 °C; use the underfloor-heating type and a suitable vapor barrier;

  • Kitchen and bathroom: only the waterproof type, and waterproofing must be applied to the substrate first;

  • Heavy loads: widen furniture feet with pads (≥50 mm); place a clear mat under wheeled chairs;

  • Thresholds: use a T-profile transition strip between different materials, 5 gap;

  • Floor boxes and pipe penetrations: cut before laying, 10 clearance around the hole, fit a collar.

05Quality Acceptance

Table 5-1 Acceptance requirements

Item

Requirement

Test method

Surface flatness

≤2 mm/2 m

2 m straightedge

Step at joints

≤0.2

Hand feel + feeler gauge

Joint straightness

≤1 mm/2 m

String line

Hollow sound / creaking

No obvious hollow sound, no movement

Walk the whole floor

Expansion gaps

8–10 at all walls, continuous

Lift the skirting and spot check

Color difference

Not discernible within the same space

Visual in daylight

06Common Problems

Table 6-1 Defects

Symptom

Main cause

Treatment and prevention

Hollow sound when walked on, click profiles break

Uneven substrate, no vapor barrier

Level to ≤2 mm; full vapor barrier

Floor bulges, blisters

No expansion gap; swelling from moisture

8–10 at walls; break at doorways

Joints open up

Air too dry; click not closed

Keep RH 40–70 %; close with a pull bar

Local edge lifting

Ridges or grit on the substrate

Clean and scrape before laying

Sandy sound when walking

Grit left on the substrate

Vacuum before laying

Floor discolors

Direct sunlight, poor vapor barrier

Shade the glazing; use a compliant barrier

Distortion after underfloor heating

Heated too fast, over-temperature

Heat gradually, ≤27 °C

07Product Storage and Handling

image.png

Figure 2 Stacking Keep the original packaging, store flat and indoors; never stand planks against a wall (they bow and will not close after installation).

Table 7-1 Storage conditions

Item

Requirement

Note

Site

Indoors, dry, out of direct sunlight

UV discolors the surface

Temperature

10 – 30 °C

Clicks become brittle at low temperature

Stacking

Flat, original packaging, ≥100 off the floor

Stack height ≤1.0 m

Acclimatization

24 – 48 h in the installation room

Open only after reaching room temperature

Incompatible goods

No heavy loads on top; never stand against a wall

Distortion is irreversible

Recommended stock life ≤12 months; opened part-packs must be stored flat with the ends aligned, never upright.

08Transport and Safety

  • Load flat in the original packaging, stack ≤1.2 m, strap down;

  • Avoid sun and rain; after transport in winter, acclimatize indoors for 48 h before opening;

  • Two people lift by the edges; never drag;

  • Wear goggles and a mask when cutting;

  • Ventilate during installation; note the solvent odor with adhesive types.

09Appendix: Checklist

9.1 Goods-in Inspection

  • □Size, thickness, batch number and color code match

  • □Click profile complete, no missing teeth, no chipped edges

  • □Planks flat, no scratches

  • □Packaging intact and dry

  • □One batch number per space

9.2 Before Installation

  • □Substrate flatness ≤2 mm/2 m

  • □Substrate moisture content within limits

  • □Vapor barrier, skirting and transition strips on site

  • □Flooring acclimatized for at least 24 h

  • □Windows and doors fitted; no wet trades running

10Frequently asked questions

Can I install it over existing tile?

Yes, if the tile is well bonded with no hollow spots, flat to 2 mm over 2 m and joints within 1 mm. Grind high points, fill grout lines, then lay the barrier. The floor rises 4–6 mm, so check door clearance and skirting depth.

Do I need an extra underlay?

On concrete the vapor barrier is enough. For a softer feel add 1–2 mm IXPE, but the softer the pad the more load concentrates on the click and the sooner seams open. Recalculate door gaps if you add one.

How long should the flooring acclimate?

Twenty-four hours flat in the room, or 48 hours with large day-night swings. Do not stack against external walls, radiators or in direct sun, or one side warms first and the floor arches toward it.

Can it be used in a kitchen or bathroom?

A waterproof core is not a waterproof joint. It works in dry and semi-dry areas with a sealed threshold, but standing water passes through the click into the substrate. Avoid shower rooms and laundries.

Floating or glue-down — which is better?

Floating is standard for homes and offices: fast and repairable plank by plank. Above 100 m², with runs over 12 m, under heavy traffic or fast heating, add movement breaks or use full-spread adhesive.

Why do the joints open after a few months?

Usually gaps packed with mortar or left-over spacers, a pad that is too soft, an uneven substrate, or no acclimation. An unclicked joint cannot be pressed back — lift that row, refit it and clear the wall gap.

About Pandaboard

Guangzhou Panda Commercial Development Co., Ltd. · Pandaboard / PEIDA

We manufacture and export gypsum board, mineral fiber and fiberglass ceiling tiles, calcium silicate and magnesium oxide boards, fiber cement board, aluminum ceilings, WPC and SPC wall panels, exterior decking, fencing and handrails, together with the matching grid and framing systems. The methods on this page are compiled from product behaviour and standard trade practice; for any project, follow the approved drawings, local codes and the specification confirmed on your order.

Website: www.pandamanufacturer.com Contact sales: contactus

Send your specification for a quotationView our full product range

Guangzhou Panda Commercial Development Co., Ltd. · Pandaboard / PEIDA
This guide is technical information for specifiers and installers; it does not replace project drawings or local codes.

Guangzhou Panda Commercial Development Co.,Ltd. is a company based in Guangzhou, China.
We have more than 20 years experience in the production and export of wall and ceiling system products.

Quick Links

Contact Us

 Email:  sales@pandamanufacturer.com
 Tel: +86-13580480068
 WhatsApp: +8613580480068
Address: Unit 1310, 13/F, South Tower of Xijiao Xieli Business Centre,No. 159, Middle of Qiaozhong Road, Liwan District, Guangzhou City, Guangdong Province, China

Subscribe To Our Newsletter

Promotions, new products and sales. Directly to your inbox.
 
Copyright © 2024 Guangzhou Panda Commercial Development Co., Ltd. All Rights Reserved. | Sitemap. Privacy Policy. Supported by leadong.com